Hi,
Problem in inserting Phase difficulty and labor factors -
Say if you run Project Hours report by category, then its hard to show phase labor factors and difficulty factor. Since running the report by Category will included items from different phases.
Its better to show Phase factors (difficulty and labor) seperately in Project Hours report as sub report.
I have created a custom report called (project phase factors) which shows Project phase difficulty and labor factors only. You can customize this report as you want.
What you have to do -
- Create a custom report based on existing project hours report.
- In the Report Footer section add a subreport control.
- Bind the sub report to the project phase factors report.
- Publish the Report.
You can download the custom report from here
Project's Phase factors
Hope it helps.