Custom report Importing –
There is known bug (#5766) relating to importing custom reports we are aware of. These are steps to reproduce: -
- Create a custom report within a custom report category
- Export the report to .zip file
- Go to another machine
- Import the .zip file
- This custom Report is listed in "Unassigned".
- Re-import the .zip file. The report disappears.
This bug will be fixed in an upcoming service pack.
These steps will work correctly now –
- Create a custom report on your machine (do not create in a custom report category – use one of the standard built in categories)
- Export the report
- Ask your coworker to import this report
- The report should appear correctly
Contract Report –
How did you rename the Phase?
Did you rename phase within the project or in Navigator. In Navigator phases can be renamed on the Setup tab – this change applies to the MasterTable and will impact only new projects and not existing projects.
Make sure you rename the phase within the projects UI.
- Open project in Text
- Click D-Tools | Options
- Click Add Phase
- In Phases in Project select Phase and click Rename
- Save Project and Run Report (reports run only of data which is saved)
Correct.JPG
rename option.JPG
Hope it helps.