Thumbs down Misc. Costs don't carry over via Quicklinks

I've added charges and discounts to the MISC COST tab of the Project Options - and I've noticed this area DOES NOT transfer into Quickbooks via QuickLinks at all.
  Reply With Quote
Old 03-28-2008, 12:11 PM   #2 (permalink)
slemay
Guest
 
Posts: n/a
Default

Bump...

Guys!??!?! Is this going to be fixed in 5.2 please???? This is VERY annoying and I'm surprised no one else has found this previously.
  Reply With Quote
Old 03-28-2008, 02:43 PM   #3 (permalink)
Certified Partner
 
Kevin Mikelonis's Avatar
 
Join Date: Mar 2006
Posts: 364
Kevin Mikelonis has a spectacular aura aboutKevin Mikelonis has a spectacular aura aboutKevin Mikelonis has a spectacular aura about
Default

Misc Costs have never done anything more than add dollars to the bottom line of the project.

It is important to know that misc costs do not affect 'cost' of the job either as they do not go to the cost side of the Gross Profit Reports.

If you have something to have accounted for by way of cost and price in the project that is out of the ordinary, add it through the database.

We have used this field for creative things like engineering change order price adjustments that keep totals in line, but nothing more.

Unfortunatley, its only been through the use of this field that users discovers its shortcomings.

Knowing the database's structure and behavior is key to manipulating the database and projects to get hat you want and expect.

What specific application are you using Misc Costs for? Perhaps I can give you a better alternative to use moving forward.

As for discounts in projects, here is info from a thread on how to do discounts:

++++++++++++++++++++++++++++++++++++++++++++++++++ +

When you discount, the money has to leave from somewhere in order for accounting, job costing, and available hours to do the work to all line up.

This all comes down to keeping the management reports for hours by phase and gross profit by phase accurate and not misleading.

Since you are ambivolent about where the money comes from, let's leave labor out of it so that you do not have to fight with having less hours via dollars than your hours reports and work orders tell you you have.

My assumption here is that you want to do more with D-Tools than just create proposals and drawings.

That being said, it's really important and benficial to the management of your business to do this in a way that works with the numbers and hours, sales tax is an issue too!

So here is my solution:

Add a phase in setup called 'DISCOUNTS' and check the box 'Ignore Project Defaults for this Phase'

Create a Zone in your Zones list within Setup called 'DISCOUNTS'

Create a Category in your Category list within MMPD/Administration called 'DISCOUNTS' and make it an 'Equipment Type' Category

In MMPD, create a new item where:

CAT = DISCOUNTS
TYPE = PROJECT
MFG = YOUR COMPANY NAME
MODEL = PREFERED CUSTOMER DISCOUNT
DESCRIPTION = "Because I love you so much my dear customer, I bequeath to you this golden discount, cherish it, and know I am yours forever"
Unit Cost = 0
Unit Price = 0
Phase = DISCOUNTS

Now add this new item to your project, in the zone 'DISCOUNTS' and to any location, or even create a location called Discounts and you can position that at the end of the project location list so it appears at the end of the proposal.

When your are prompted that there is no price for the item, correct the unit price with a negative number which is your discount!

Remember that Sales tax will be affected too (this is a good thing!) so your total discount will be more than your negative entry, but that will come out of the sales tax at the end of the proposal report.

What's really nice about all this, is the discount is not only clearly apparent in your Proposal, but it is also a stand out in all your financial reports, it does not become a global adjustment that lives on through future changes to the project, it covers the sales tax issue, and can be pushed into a sales order and make it over to Quickbooks -BRILLIANT!
__________________
Kevin Mikelonis
Process Dealer Services Group
D-Tools Certified Partner
PO Box 3443
Paso Robles, Ca
805.275.2308
www.processdsg.com
info@processdsg.com

Stuff That Works

Last edited by Kevin Mikelonis; 03-28-2008 at 02:49 PM.
Kevin Mikelonis is offline   Reply With Quote
Old 03-28-2008, 04:35 PM   #4 (permalink)
Program Manager
 
RandyB's Avatar
 
Join Date: Mar 2006
Location: Concord, CA
Posts: 353
RandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond reputeRandyB has a reputation beyond repute
Default Questions about use of misc costs

Originally Posted by slemay View Post
Bump...

Guys!??!?! Is this going to be fixed in 5.2 please???? This is VERY annoying and I'm surprised no one else has found this previously.
Shawn,

The feature set for 5.2 is fixed at this point and we are in final testing, so nothing new is going to be included. We are, however, going to be doing some serious redesign work soon with regards to Quicklinks, so this issue will be taken care of then.

Questions:
a) Do you typically have many miscellaneous costs in a project, or just a couple?
b) What types of things do you include as miscellaneous costs?
c) Why do you put them as miscellaneous costs and not as a regular line item? Is it a display issue (you'd like to see them in a separate section on proposals), or is there another reason?

Any additional information about what you use misc costs for would be helpful for future development.

Best regards,

Randy Bownds
Program Manager
D-Tools, Inc
RandyB is offline   Reply With Quote
Old 03-29-2008, 02:58 PM   #5 (permalink)
slemay
Guest
 
Posts: n/a
Default

Well - most commonly we use it for DISCOUNTS... but we may have to go with what Kevin is suggesting.

Once in a blue moon we do one time items... for example we did a FIBER pull a few weeks ago - and I doubt we'll do any more in the next year... it was to link a front building with a rear building at about 500'... so it was a special case and we were just passing on the cost from another vendor.

I like the DISCOUNT showing up in the end of the project under the subtotals... so that's why we'd done discounts there typically. People usually skip to the very end... so I wanted it to be obvious.
  Reply With Quote
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
another misc cost question ekalpakoff General Section 1 09-01-2009 11:54 PM
Shipping and Taxes ekalpakoff D-Tools System Integrator 5 3 07-29-2009 08:25 PM
Ignore Misc costs on a per item basis Gurkha SI Navigator Section 0 10-30-2008 10:16 AM
Misc Costs Erroneously Included in Chg Order jjbrasuell Business Manager 0 04-01-2008 05:51 PM
Misc costs in Change Order report dharmonyav Reports and Reporting Center 3 09-18-2007 03:50 PM