Originally Posted by David_Haddad
|
|
Does anyone know if refreshing packages work? I changed some pricing on some packages but was unable to update pricing in a project by selecting 'refresh from master table'. Tried is several times with no luck. I had to delete every single package and drag it back in.
|
David;
Did you find a solution for this issue. It is a pertinent one!
I also am updating a package and expected my project to reflect those changes.
I have been unsuccessful in achieving this goal, it is my preference to avoid replacing the existing project with a new one, nor is it agreeable to revert to my original package the project still believes is current, despite not existing in the MMPD.
Thanks